Step -9: Make sure to apply the below global change or else your cost may not Export to other machines – Thanks to Korai from Planning Team for helping here Like here, could you do it for Structure and Finishing? As you can see, Apply this to the rest of the activities by following the same global change method. Step -7: Review the global change and click Commit Changes. Like here, I have 3 activities for hardscaping, and I divided 12000 $ by 3 and put this value to the program by a global change as below. Step -6: After that, I filtered the same activities in all areas and divided the cost from BOQ to that number. Step -5: This is a just Demo BOQ from which we will upload the cost. Step -4: Apply this resource to all activities. Step -3: Put Price/Unit, Default Units/Time & Max Units/Time = 1 Step – 1: Below snap of a Demo plan without Budgeted Cost and Budgeted Units The following steps were performed to load the cost from BOQ.